1. Entering high -rise scaffolding, the various materials used must meet the quality requirements.

2. The foundation of the high -rise scaffolding must be firm. Calculate the previous calculation, meet the load requirements, and set up according to the construction specifications to take drainage measures.

3. The technical requirements of the erection of the scaffold should meet the relevant specifications.

4. We must attach great importance to various structural measures: scissors, knotted nodes, etc. should be set up as required.

5. Horizontal closed: From the first step, every step or two steps should be paved with a palette or a handle of the foot. There are also security bottoms between the rods and the walls every four steps.

6. Vertical closed: From the second to the fifth step, each step is required to set up 1.00m high protection sample railings and feet or setting nets on the inside of the vertical rod. In addition to the protection barrier, all the above steps should be set up with a safe or safe stand; in the intensive area of the street or residential area, the second step should be set up from the second step.

7. The set of scaffolds should be higher than the top of the building or more than 1.5m of the operation surface, and enclosure.

8. The steel pipes, buckles, scooters and connection points on the scaffolding of the scaffolds shall not be dismantled at will. When necessary during construction, the person in charge of the construction site must be approved by the person in charge of the construction site and takes effective measures. After the process is completed, it must be restored immediately.

9. Before the use of scaffolding, the person in charge of the construction site shall organize the inspection and acceptance, pass the acceptance and fill in the submission form. During the construction process, professional management, inspections and warranty should be available, and regular settlement observations should be performed, and reinforcement measures should be taken in time.

10. When the scaffolding is demolished, check the connection with the building first, and remove the remaining materials and debris on the scaffolding. The materials should be passed down or lifted to the ground, and clearly. It is not allowed to adopt a step -by -step demolition method, and it is strictly forbidden to throw or push (pull) to remove it.

11. To dismantle the scaffolding, a warning area should be set up and a special person should be sent to alert. In the case of high -level wind and harsh climate, the scaffolding should be stopped.

12. For the foundation, the foundation is not usual, please use the base foot to achieve a balance. The foundation must have the ability to bear scaffolding and work at work.

13. The staff must have a seat belt in the construction and high -altitude work. Please install a safety net around the work area to prevent heavy objects from falling and hurting others.

14. The components and accessories of the scaffolding are strictly prohibited from severe falls and collisions during transportation and storage; when overlapping and disassembling, it is strictly forbidden to leave from a high place. When disassembling, it should be operated from top to bottom in order.

15. Pay attention to safety in the process of use. It is strictly forbidden to play and play on the shelf to prevent accidents.

16. Although work is important, safety and life are more important. Please keep in mind the above.